From page 2 of the linked report:

The original cost estimate to complete the Cannon St. Cycle Track was $867,200. To date, the total expenditures on this project, including minor modification in 2016 is $524,100.

Kevin's question: How many other City of Hamilton projects came in under budget by that kind of percentage?

Answer: Approximately zero.

Comment edited by KevinLove on 2017-04-12 17:02:25

Permalink | Context