By Noted (anonymous) | Posted March 09, 2015 at 11:32:08 in reply to Comment 110054

2010 Metrolinx King-Main BCA Costing:

Option 1: Full BRT 14.2 km = $220M CDN 2008 ($245M CDN 2015)
Option 2: Full LRT 14.2 km = $830M CDN 2008 ($923M CDN 2015)
Option 3: Phased LRT 9.3 km = $600M CDN 2008 ($667M CDN 2015)

metrolinx.com/en/docs/pdf/board_agenda/20100219/hamilton_king-main_bca-final.pdf

Rapid Ready allowed for a capital cost margin of plus/minus 20% (p. 5).

hamilton.ca/NR/rdonlyres/76D38C17-DC96-4C54-8E55-3A6EA1C71D73/0/Feb25EDRMS_n414203_v1_5_1_PW13014.pdf

So full LRT alone could (using Metrolinx's 2010 numbers) come in at $1.1B, even before the HSR ask.