By kevlahan (registered) | Posted September 28, 2016 at 14:25:50 in reply to Comment 120166

The construction will almost certainly be staged and the city will insist that two major intersections can't be shut down at the same time (the Metrolinx rep told me this at the PIC). However, unfortunately, the precise details of construction won't be known until the contract has been signed, which will likely be sometime in 2018.

The successful bidder will be responsible for the 70% remaining engineering design and for determining the details of the construction schedule.